Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

create/ draw a value stream map You have measured the cycle time, change over time and up time of each of the processes, and found:

image text in transcribed
create/ draw a value stream map
You have measured the cycle time, change over time and up time of each of the processes, and found: - Wet Mixing: Cycle Time - 140 sec.; Change Over Time- 360 sec.; Up Time-99\% - Complete Mixing: Cycle Time -220 sec.; Change Over Time - 360 sec.; Up Time 98% - Panning: Cycle Time -30 sec.; Change Over Time - 0 sec.; Up Time 100% - Baking: Cycle Time - 35 min.; Change Over Time -600 sec.; Up Time 82% - Inspection: Cycle Time - 20 sec.; Change Over Time- 0 sec.; Up Time -100\% - Packaging: Cycle Time -10 sec.; Change Over Time - 0 sec.; Up Time 91% You operate weekdays, one shift of ten hours per day. You measure the WIP between the work stations. There are 3,000 eggs in Raw Material Storage. The count after each station is: the equivalent of 1,800 eggs after Wet Mixing, 540 eggs after Complete Mixing, 400 eggs after Panning, 60 eggs after Baking, 0 eggs after Inspection, and 900 eggs after Packaging. You measure the yield of each work station. The yield measures are: - Wet Mixing: 94% - Complete Mixing: 94% - Panning: 100% - Baking: 88% - Inspection: 93% - Packaging: 100%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions