Question
Create illustrations of for example control charts for questions 1.2, 2, 3 1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $
Create illustrations of for example control charts for questions 1.2, 2, 3
1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date: 10 days
1.1) Perform the following analyses of the project based on the data given above. a. Cost Variance
CV = BCWP - ACWP
CV = $6,400 - $7,800
CV = -$1,400
Cost Variance is negative, indicating that the project is over budget. b. Schedule Variance
SV = BCWP - BCWS
SV = $6,400 - $8,333
SV = -$1,933
Schedule Variance is negative, indicating that the project is behind schedule. 1.2) Plot an S-Curve and show CV and SV on it.
1.3) Interpret results to explain the project status
2)Explain the purpose of a Control Chart being as detailed as possible with words and use illustrations as well to explained it better
3)Please explain why large initial separations on the EV S-Curve between the lines for ACWP and BCWP with BCWP above the ACWP may be an indicator of excessive front loading. Use detailed words and explanations and illustrations to explain it
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started