Creger Corporation, which makes landing gears, has provided the following data for a recent month: Budgeted production 1,400 gears Standard machine-hours per gear 4.9 machine-hours
Creger Corporation, which makes landing gears, has provided the following data for a recent month:
Budgeted production | 1,400 | gears | |
Standard machine-hours per gear | 4.9 | machine-hours | |
Budgeted supplies cost | $ | 5.50 | per machine-hour |
Actual production | 1,800 | gears | |
Actual machine-hours | 9,300 | machine-hours | |
Actual supplies cost (total) | $ | 49,642 | |
Required:
Determine the rate and efficiency variances for the variable overhead item supplies and indicate whether those variables are favorable or unfavorable.
(Input all amounts as positive values.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started