Critical Path Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path Method Links to an external site. ,
Critical Path
Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path MethodLinks to an external site., Gantt ChartLinks to an external site., and PERTLinks to an external site., and read Chapter 6: Developing a Project Schedule from your course textbook.
Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path?
Work Packages
ID | Description | Predecessor | Durations |
A | Survey Site | None | 2 Days |
B | Excavate Site | A | 4 Days |
C | Install Power Lines | B | 3 Days |
D | Install Drainage | B | 2 Days |
E | Pour Foundation | C, D | 3 Days |
Here is what I have does it look correct?
6 0 A 2 0 Site Survey 0 2 2 Exavate Site 4 6 11 E 14 0 Pour Foundation 11 3 14 C 9 Install Power Lines 3 11 D 8 Install Drainage 2 8Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started