Cullumber Manufacturing Inc. is installing a new plant at its production facility. It has incurred these costs:
Fantastic news! We've Found the answer you've been seeking!
Question:
Cullumber Manufacturing Inc. is installing a new plant at its production facility. It has incurred these costs:
Cost of the manufacturing plant (cost per supplier's invoice plus non-recoverable taxes) | $2,490,000 | |
Initial delivery and handling costs | 210,000 | |
Cost of site preparation | 608,000 | |
Consultants used for advice on the acquisition of the plant | 107,000 | |
Interest charges paid to supplier of plant (indirect financing charges for amounts borrowed by supplier) | 209,000 | |
Estimated dismantling costs to be incurred after seven years | 307,000 | |
Operating losses before commercial production | 405,000 |
Determine which costs Cullumber Manufacturing can capitalize in accordance with IAS 16.
According to IAS 16, following costs can be capitalized: | ||
---|---|---|
select a type of cost Consultants' FeesCost of Site PreparationCost of the Manufacturing PlantEstimated Dismantling Costs to be Incurred after Seven YearsInitial Delivery and Handling CostsInterest ChargesOperating Losses before Commercial Production | $enter a dollar amount | |
select a type of cost Consultants' FeesCost of Site PreparationCost of the Manufacturing PlantEstimated Dismantling Costs to be Incurred after Seven YearsInitial Delivery and Handling CostsInterest ChargesOperating Losses before Commercial Production | enter a dollar amount | |
select a type of cost Consultants' FeesCost of Site PreparationCost of the Manufacturing PlantEstimated Dismantling Costs to be Incurred after Seven YearsInitial Delivery and Handling CostsInterest ChargesOperating Losses before Commercial Production | enter a dollar amount | |
select a type of cost Consultants' FeesCost of Site PreparationCost of the Manufacturing PlantEstimated Dismantling Costs to be Incurred after Seven YearsInitial Delivery and Handling CostsInterest ChargesOperating Losses before Commercial Production | enter a dollar amount | |
select a type of cost Consultants' FeesCost of Site PreparationCost of the Manufacturing PlantEstimated Dismantling Costs to be Incurred after Seven YearsInitial Delivery and Handling CostsInterest ChargesOperating Losses before Commercial Production | enter a dollar amount | |
$enter a total amount |