Culver Manufacturing spends 55 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.4 hours. Calculate the manufacturing cycle efficiency. (Round answer
Culver Manufacturing spends 55 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.4 hours. Calculate the manufacturing cycle efficiency. (Round answer to 1 decimal place, e.g. 5.1%.) Manufacturing cycle efficiency Enter the manufacturing cycle efficiency in percentages rounded to 1 decimal place %