Cumulative Average - Time Learning Curve ONLY NEED QUESTION 3 Pohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design

Cumulative Average-Time Learning Curve ONLY NEED QUESTION 3
Pohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design is subject to an 80 percent learning rate. Assume that the first unit produced takes 500 hours, and direct labor is paid an average of $30 per hour.
Required:
1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of: one engine, two engines, four engines, eight engines, sixteen engines, and thirty-two engines. (Round hour answers to two decimal places.)
Cumulative Number of Units Cumulative Average Time per Unit in Hours Cumulative Total Time: Labor Hours
1 fill in the blank 1
500
fill in the blank 2
500
2 fill in the blank 3
400
fill in the blank 4
800
4 fill in the blank 5
320
fill in the blank 6
1,280
8 fill in the blank 7
256
fill in the blank 8
2,048
16 fill in the blank 9
204.80
fill in the blank 10
3,276.80
32 fill in the blank 11
163.84
fill in the blank 12
5,242.88
2. What is the total labor cost if Pohlman manufactures the following number of engines: one, four, or sixteen? (Round your answers to the nearest dollar.)
Cost for manufacturing one engine $fill in the blank 13
15,000
Cost for manufacturing four engines $fill in the blank 14
38,400
Cost for manufacturing sixteen engines $fill in the blank 15
98,304
What is the average cost per engine for the following number of engines: one, four, or sixteen?
Average cost per system for one engine $fill in the blank 16
15,000
Average cost per system for four engines $fill in the blank 17
9,600
Average cost per system for sixteen engines $fill in the blank 18
6,144
3. What if Pohlman is preparing a bid to build 16 engines? If necessary, round your answers to both parts to the nearest dollar.
Calculate budgeted labor cost for an engine design which Pohlman has built before (assume that 16 of these engines had been made previously and the first unit took 500 hours).
$fill in the blank 19
Calculate budgeted labor cost for a new engine design that Pohlman's workers have never made before (assume the first unit will take 500 hours).
$fill in the blank 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions