Question
1 Approved Answer
Cumulative Percentage Complete 1 2 3 4 Task 1 40 62% 85% 100% Task 2 25% 75% 90% Task 3 7% 7% 45% Task
Cumulative Percentage Complete 1 2 3 4 Task 1 40 62% 85% 100% Task 2 25% 75% 90% Task 3 7% 7% 45% Task 4 10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI? FCAC (3 Methods) Assume the project continues to completion with no changes to the CPI, what is the expected FCAC? Is this under or over budget? Assume the project continues based on its original budgeted costs, what is the expected FCAC? Is this under or over budget? Using the SPI, is this project is on schedule? Bonus points (+5): Assume the project continues based on its original budgeted cost except that there is a $7,500 change order from the customer for an outdoor kitchen to be added to Task 3. What are the new expected FCAC's? Do you think it can still be finished in the 5- week time period? Why/why not?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started