Current Attempt in Progress Assembly line workers at Sandhill Manufacturing worked a total of 14100 direct labor hours to produce 38200 units. The standard for
Current Attempt in Progress Assembly line workers at Sandhill Manufacturing worked a total of 14100 direct labor hours to produce 38200 units. The standard for producing one unit is 15 minutes at a wage rate of $12.1. If the actual wage rate was $12.6 per direct labor hour, Sandhill's direct labor rate variance is $7050 favorable. $4775 unfavorable. $7050 unfavorable. $4775 favorable. Save for Later Attempts: 0 of 1 used