Current Attempt in Progress Assembly line workers at Sunland Manufacturing worked a total of 10700 direct labor hours to produce 43600 units. The standard for producing one unit is 15 minutes at a wage rate of $ 11.9. If the actual wage rate was $ 12.40 per direct labor hour, Sunland's direct labor efficiency variance is $ 2480 unfavorable. $ 2380 unfavorable. $ 2480 favorable. $ 2380 favorable. Assembly line workers at Blossom Manufacturing worked a total of 12100 direct labor hours to produce 36200 units. The standard for producing one unit is 15 minutes at a wage rate of $ 10.1. If the actual wage rate was $ 10.6 per direct labor hour, Blossom's direct labor rate variance is $ 6050 favorable. $ 6050 unfavorable. $ 4525 favorable. $ 4525 unfavorable. Crane Creations purchased 9400 feet of copper tubing at a price of $2.50 per foot and used 9600 feet during the period. The standard quantity allowed for the units produced is 9700 and the standard price of the copper tubing is $2.30 per foot. What is Crane Creations' direct materials quantity variance for the period? $230 favorable $460 favorable $230 unfavorable $690 favorable Wildhorse Creations purchased 8000 feet of copper tubing at a price of $2.60 per foot and used 8320 feet during the period. The standard price of the copper tubing was $2.80 per foot. What is Wildhorse Creations direct materials price variance for the period? or $1664 favorable $1664 unfavorable $1600 unfavorable $1600 favorable Blossom Manufacturing Company purchased 14200 switches to make 6100 units. The standard allows for 2 switches per unit. The company actually used 14700 to produce the 6100 units. Blossom budgeted $0.70 per switch but had to pay $0.75 per switch. What is Blossom's direct materials price variance for the period? $505 unfavorable $710 unfavorable $610 unfavorable $735 unfavorable