Current Attempt in Progress Crane Company provided the following information from its accounting records for 2019. Estimated production 100000 labor hours Actual production 86000 labor
Current Attempt in Progress Crane Company provided the following information from its accounting records for 2019. Estimated production 100000 labor hours Actual production 86000 labor hours Budgeted overhead $900000 Actual overhead $860000 How much is the overhead application rate if Crane Company bases the rate on direct labor hours? $8.60 per hour $9.00 per hour $10.47 per hour O $10.00 per hour