Current Attempt in Progress During March, Patt, Inc. purchases and uses 8,800 pounds of materials costing $35,640 to make 4,000 tiles. Patt's standard material cost
Current Attempt in Progress During March, Patt, Inc. purchases and uses 8,800 pounds of materials costing $35,640 to make 4,000 tiles. Patt's standard material cost per tile is $8 (2 pounds of material $4.00). Compute the total, price, and quantity material variances for Patt, Inc. for March. Identify whether the variance is favorable or unfavorable? Total Materials Variance $ Materials Price Variance $ Materials Quantity Variance $