Currently, a consulting company has five jobs in its backlog. Determine the schedule by using the FCFS rule. Customer Time Since Order Arrived (days ago)
Currently, a consulting company has five jobs in its backlog. Determine the schedule by using the FCFS rule. Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 15 25 29 B 12 16 27 C 5 14 68 D 10 10 48 E 0 12 80 The order customers will be served are as follows: Group of answer choices A, B, C, D, E A, C, D, B, E B, A, C, D, E A, B, E, D, C A, B, D, C, E