Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased the tile and the contractor will be reimbursed for

Customer hires a contractor to tile 40 identical rooms in his office building. The customer purchased the tile and the contractor will be reimbursed for labor only. The contractor assumes he can complete one room per day at eight hours per day and at a cost of $1000/day or $1000 per room The planned cost is $40,000 and the planned duration is 40 days

Current status At the end of 6 weeks (30 days). The contractor has completed 24 rooms at a cost of 27,000. This includes a freak accident where the tiles for two offices had to be removed & replaced.

Create a project status table similar to the one below and calculate the values for: PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC, TCPI

Round any indices to two decimals

Planned value (PV)

Earned value (EV)

Actual cost (AC)

Budget at Completion (BAC)

Estimate to Complete (ETC)

Variance at Completion (VAC)

To Complete Performance Index (TCPI)

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI)

Schedule Performance Index (SPI)

Estimate at Completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Creative Accounting, Fraud And International Accounting Scandals

Authors: Michael J. Jones

1st Edition

0470057653, 9780470057650

More Books

Students also viewed these Accounting questions