Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Cyber Construction Company uses the cost-to-cost method to record revenues and gross profit for all of its projects. Cyber began a three-year project on January

Cyber Construction Company uses the cost-to-cost method to record revenues and

gross profit for all of its projects. Cyber began a three-year project on January 1, 2019. Costs for the project expected to total $2,100,000. Cyber will receive a total of $3,600,000 in revenue for this project.

Data for the project appears below:

2019 2020 2021

Costs to date $ 840,000 $1,365,000 $2,100,000

Estimated remaining costs 1,260,000 735,000 -

Progress Billings during the year 1,400,000 1,000,000 1,200,000

Cash collected during the year 1,050,000 940,000 1,610,000

Calculate Cybers revenue and gross profit for each of the three years.

Place all answers on the lines provided and show all work in the space below.

Revenue Gross Profit

2019

2020

2021

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Benefit Analysis With Reference To Environment And Ecology

Authors: James H. Meisel, K. Puttaswamaiah

1st Edition

1138521329, 978-1138521322

More Books

Students also viewed these Accounting questions