Cyber Construction Company uses the cost-to-cost method to record revenues and gross profit for all of its projects. Cyber began a three-year project on January
Cyber Construction Company uses the cost-to-cost method to record revenues and
gross profit for all of its projects. Cyber began a three-year project on January 1, 2019. Costs for the project expected to total $2,100,000. Cyber will receive a total of $3,600,000 in revenue for this project.
Data for the project appears below:
2019 2020 2021
Costs to date $ 840,000 $1,365,000 $2,100,000
Estimated remaining costs 1,260,000 735,000 -
Progress Billings during the year 1,400,000 1,000,000 1,200,000
Cash collected during the year 1,050,000 940,000 1,610,000
Calculate Cybers revenue and gross profit for each of the three years.
Place all answers on the lines provided and show all work in the space below.
Revenue Gross Profit
2019
2020
2021
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started