Question
Cycle Time and Velocity Bemidii Company has the following data for one of its production departments: Theoretical velocity: 210 units per hour Productive minutes available
Cycle Time and Velocity
Bemidii Company has the following data for one of its production departments:
Theoretical velocity: 210 units per hour |
Productive minutes available per year: 39,000,000 |
Annual conversion costs: $312,000,000 |
Actual velocity: 84 units per hour |
Required:
1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent.
Actual cycle time | fill in the blank 1 | minutes per unit |
Standard cost per minute | $fill in the blank 2 | per minute |
Conversion cost per unit | $fill in the blank 3 | per unit |
2. Calculate the ideal conversion cost per unit using theoretical cycle time and the standard cost per minute. If required, round your intermediate calculations and final answers to two decimal places.
Theoretical cycle time | fill in the blank 4 | minutes per unit |
Conversion cost per unit | $fill in the blank 5 | per unit |
What incentive exists for managers when cycle time costing is used?
To reduce cycle timeTo increase cycle timeTo keep cycle time constant
3. What if the actual velocity is 147 units per hour? What is the conversion cost per unit? If required, round your intermediate calculations and final answers to two decimal places.
Actual cycle time | fill in the blank 7 | minutes per unit |
Conversion cost per unit | $fill in the blank 8 | per unit |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started