d) Assuming that the probability distribution of the length of the critical path can be approximated by a normal distribution with the mean and

image text in transcribedimage text in transcribed

d) Assuming that the probability distribution of the length of the critical path can be approximated by a normal distribution with the mean and standard deviation calculated in part (b), calculate the probability that the project can be completed within 79 weeks. [4 points] e) What is the probability that the project will be completed between 78 and 82 weeks? [4 points] f) Answer the project manager's question: "I want to tell the client that there is a 19.77% chance that the project will take longer than X weeks to be completed - what figure should I give them (i.e. find X)?" [4 points]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Gail Fayerman

1st Canadian Edition

9781118774113, 1118774116, 111803791X, 978-1118037911

More Books

Students also viewed these Accounting questions

Question

Find the radius of convergence of? 1.2.3 1.3.5 (2n-1) r2n+1 -1

Answered: 1 week ago