d. Partnership and Collaboration h. Expert System: 13. Use the PERT diagram below to find the ES, EF, LS, LF, Slack Time, and the direction
d. Partnership and Collaboration h. Expert System: 13. Use the PERT diagram below to find the ES, EF, LS, LF, Slack Time, and the direction of the Critical Path. A 7 F 17 O 11 B 10 D 14 G 14 E 6 EF LS LF S/Time CP? Task ES Time LF 10 17 28 17 28 32 40 1 7 8 52 1565