D Question 11 0.5 pts If the project's performance is expressed by this graph, which of the following is true about the project performance? EV
D Question 11 0.5 pts If the project's performance is expressed by this graph, which of the following is true about the project performance? EV $ AC PV Time The project is performing ahead of schedule and under budget The project is performing ahead of schedule and over budget The project is performing behind schedule and over budget O The project is performing behind schedule and under budget