Question

1 Approved Answer

Dahlia Simmons Dahlia Simmons, CFO of Dahlia Enterprises, is analyzing a new project to sell solar powered batteries for cell phones. Dahlia has estimated the

Dahlia Simmons
Dahlia Simmons, CFO of Dahlia Enterprises, is analyzing a new project to sell solar powered batteries for cell phones. Dahlia has estimated the following probability distributions for the variables in the project:
Probability: 10%30%45%?
Industry demand: 80,000,00095,000,000108,000,000124,000,000
Probability: 10%20%20%25%20%?
Dahlia market share: 1%2%3%4%5%6%
Probability: 20%70%?
Initial cost: $60,000,000 $65,000,000 $72,000,000
Probability: 20%65%?
VC per unit $24 $26 $29
Probability: 15%25%40%?
Fixed costs: $20,000,000 $24,000,000 $27,000,000 $31,000,000
The unit price depends on the industry demand since a greater demand will result in a higher price. Dahlia determines that the price per unit will be given by the following equation:
Price = Industry demand /2,000,000+ $1(+/-$2)
The random "+/-$2" term represents a increase or decrease in price according to the following distribution:
Probability: 40%?
Price randomness: ($2) $2
The length of the project, tax rate, and required return are:
Project length (years): 6
Depreciation Straight Line Method with Zero scrap value
Tax rate: 34%
Required return: 14%
QUESTIONS:
1"(25 Points)
Calculate the missing probabililty (where ? appears) in the above.
Fill Table 1(shown on next sheet):
Run a Monte Carlo simulation for the project with at least 500 iterations of the calculation.
How?
Step 1: In the Simulation Analysis excel sheet, type in =Rand() in cell B37 and drag it all the way to G536 to create six columns of 500 random numbers each reflecting random probability for the following six variables: Industry Demand, Dahlia Market Share, Price per Unit, Initial Investment, Variable Cost per Unit, and Fixed Costs.
Step 2: Use the generated random probability to assign a value for each of the six variables for each iteration (e.g., if the probability for industry demand is 76%, then the industry demand would be 108,000,000). For that you need to insert an extended if statement
in cell H37, I37, K37, L37, N37, P37 and then drag the if conditions all the way to row 536. Create the appropriate calculation formula in J37, M37, O37, Q37, R37, S37, T37 and U37, and then drag the corresponding formula all the way to row 536."
2"(20 Points)
Using the 500 iterations from Table 1(which you already developed on next sheet when answering question a), do the necessary computations in Table 2(shown on next sheet) to calculate the Operating Cash Flows (OCF) for each iteration, the IRR and NPV for each iteration.
NOTE: The IRR function in Excel will return an error if the IRR of the project is too low. For example, what is the IRR if both the initial cash flow and the operating cash flows are negative? The IRR is less than -100 percent. This is not a problem when you are calculating the IRR one time since you can see the IRR is too low, but when you are running 500 or more iterations it can create a problem trying to summarize the results. Because of this, you should create an IF statement that tests if the operating cash flow divided by the absolute value of the initial investment is less than 0.1. If this is the case, the cell will return an IRR of -99.99 percent, else the cell will calculate the IRR."
3(5 Points) Using Table 3 results (automatically displayed on next sheet), create a graph of the distribution of the IRRs from the Monte Carlo simulation for different ranges of IRR. Please comment.
4(5 Points) Using Table 3 results (automatically displayed on next sheet), create a graph for the cumulative probability function for the IRR distribution. Please comment.
5(2.5 Points) What is the probability of positive NPV?
6(2.5 Points) Based on the above results, do you accept or reject the project and why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management For Farmers And Rural Managers

Authors: Martyn Warren

4th Edition

0632048719, 9780632048717

More Books

Students also viewed these Finance questions

Question

Explain the link between positive thinking and good health.

Answered: 1 week ago

Question

=+How would you change the tone of voice?

Answered: 1 week ago