Dakota enters into a contract with Avery in which Dakota will renovate Avery's house. They enter into the contract on July 1 and the contract

Dakota enters into a contract with Avery in which Dakota will renovate Avery's house. They enter into the contract on July 1 and the contract states that it is vital that the work be completed by July 31. Dakota does an excellent job but doesn't complete the job until August 14. Due to the delay Avery had to postpone a big party he was going to have in his house on August 2. It cost Avery $25,000 to reschedule the party. Avery sues Dakota for damages. Will Avery be successful? What if the contract just had the July 31 completion date but never stated that it was vital and it was customary for these types of jobs to typically run 4-6 weeks late? Would the result change?

Step by Step Solution

3.46 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

Original Contract Explicit Importance of Deadline If the contract explicitly states that completing ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Smith and Roberson Business Law

Authors: Richard A. Mann, Barry S. Roberts

15th Edition

1285141903, 1285141903, 9781285141909, 978-0538473637

More Books

Students also viewed these Law questions

Question

Discuss criminal intent and the various degrees of mental fault.

Answered: 1 week ago