Dalton Construction Company contracted to build a bridge for $8,000,000. Construction began in 2014 and was completed in 2015. Data related to the construction are:

Dalton Construction Company contracted to build a bridge for $8,000,000. Construction began in 2014 and was completed in 2015. Data related to the construction are:

2014 2015

Costs incurred during the year $2,640,000 $2,200,000

Estimated costs to complete 2,160,000 0

Dalton uses the percentage of completion method of accounting.

Answer the following questions WITH SUPPORTING COMPUTATIONS:

How much revenue should be reported in 2014?

Make the entry to record progress billings of $3,300,000 during 2014.

Make the entry to record revenue, expense and gross profit for 2014.

How much gross profit should be reported for 2015?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A Journey Into Auditing Culture

Authors: Grant Thornton United Kingdom, Susan Jex, Eddie J. Best

1st Edition

1634540565, 978-1634540568

More Books

Students also viewed these Accounting questions

Question

Write formal proposal requests.

Answered: 1 week ago

Question

Write an effective news release.

Answered: 1 week ago

Question

Identify the different types of proposals.

Answered: 1 week ago