Question
1 Approved Answer
Dandridge Incorporated planned to use 2 sq. yards of material at $6/sq. yard per unit but actuallv used 2.5 sq. yards of materials at $5.20/sq.
Dandridge Incorporated planned to use 2 sq. yards of material at $6/sq. yard per unit
but actuallv used 2.5 sq. yards of materials at $5.20/sq. yard per unit. It planned to make 1,500 units but
actually made 1,800 units. The total flexible-budget variance for materials is
O $1,800 favorable
O $1,500 favorable
0 $1,500 unfavorable
51.800 unfavorable