Question

1 Approved Answer

Darren Company uses 36,000 yards of canvas each month to make tents. It usually takes four (4) days from the time Darren orders the material

Darren Company uses 36,000 yards of canvas each month to make tents. It usually takes four (4) days from the time Darren orders the material to when it is received. If the desired safety stock is 5,000 yards, what is the re-order point? (Answer format: 25,000) no peso sign, no unit of measure!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Donald E. Kieso, Jerry J. Weygandt, And Terry D. Warfield

13th Edition

9780470374948, 470423684, 470374942, 978-0470423684

More Books

Students also viewed these Accounting questions

Question

Know when to use TPM? p-69

Answered: 1 week ago

Question

Why is failing to reject ????0 often an unreliable decision?

Answered: 1 week ago

Question

24. What effect does a lean production environment have on MRP?

Answered: 1 week ago