Data have been collected on the malfunctions and breakdowns that have caused line stoppages on a certain automated production line. Based on these data, the
Data have been collected on the malfunctions and breakdowns that have caused line stoppages on a certain automated production line. Based on these data, the mean time between failures is 4.37 hours and the mean time to repair is 24.1 min. Determine the availability of this line.