DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day Consider table below as demonstration of a resource-limited project. Assume that

DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day

Consider table below as demonstration of a resource-limited project. Assume that you cannot schedule more than eight hours of work during any day of work. A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4

DATA TABLE FOR RESOURCE LIMITED PROJECT Activity Predecessors Duration (Days) Resource Hours per Day A None 5 4 B A 3 4 C A 4 4 D A 6 3 E C 5 3 F C 6 2 G D 4 4

Identify if there are any days that involves resource conflict and give their status

How would you reconfigure the resource loading to resolve this conflict

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial ACCT2

Authors: Norman H. Godwin, C. Wayne Alderman

2nd edition

9781285632544, 1111530769, 1285632540, 978-1111530761

Students also viewed these General Management questions

Question

Describe effectiveness of reading at night?

Answered: 1 week ago

Question

find all matrices A (a) A = 13 (b) A + A = 213

Answered: 1 week ago

Question

statistics on developing a CAUTI in those of advanced age

Answered: 1 week ago