DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.
Month
1234
Throughput time (days)????
Delivery cycle time (days)????
Manufacturing cycle efficiency (MCE)????
Percentage of on-time deliveries82%77%74%71%
Total sales (units)2100201019071835
Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:
Average per month (in days)
1234
Move time per unit.6.3.4.4
Process time per unit2.32.22.12.0
Wait time per order before start
Of production20.021.926.028.0
Queue time per unit4.75.56.47.4
Inspection time per unit.8 1.11.1.8
Required:
1-a. Compute the throughput time for each month.
1-b. Compute the delivery cycle time for each month.
1-c. Compute the manufacturing cycle efficiency (MCE) for each month.
2. Evaluate the company's performance over the last four months.
3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production.Compute the new throughput time and MCE.
3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.
1-a. Compute the throughput time for each month.
1-b. Compute the delivery cycle time for each month.
1-c. Compute the manufacturing cycle efficiency (MCE) for each month.
(Round your answers to 1 decimal place.)
Throughput TimeDeliver Cycle TimeManufacturing cycle efficiency (MCE).
Month 1daysdays%
Month 2daysdays%
Month 3daysdays%
Month 4daysdays%
Evaluate the company's performance over the last four months.(Indicate the effect of each trend by selecting "Favorable" or"Unfavorable" or "None" for no effect (i.e., zero variance).
The throughput time measure displays ____________ trends
The delivery cycle time-days measure displays ____________ trends
Manufacturing cycle efficiency-days measure displays ____________ trends
3-a. (Month 5) Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production.Compute the new throughput time and MCE.
3-b. (Month 6) Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.
(Round your answers to 1 decimal place.)
Month 5Month 6
Throughput time___________ days_________ days
Manufacturing cycle efficiency (MCE)______%______%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started