DataSpan, Incorporated, implemented Lean Production and would like to redesign its performance measures accordingly. It has provided the following data sets: Required: 1.a. Compute the throughput time for each month. 1.b. Compute the delivery cycle time for each month. 1.c. Compute the manufacturing cycle efficiency (MCE) for each month. 2. Evaluate the company's performance over the last four months. 3-a. Refer to the data for month 4. Assume in month 5 the company uses Lean Production to completely elliminate the queue time, and all else remains the same as month 4 . Compute the new throughput time and MCE. 3-b. Refer to the data for month 4. Assume in month 6 the company eliminates all queue time and inspection time, and all else remains the same as month 4. Compute the new throughput time and MCE. Required: 1.a. Compute the throughput time for each month. 1.b. Compute the delivery cycle time for each month. 1c. Compute the manufacturing cycle efficiency (MCE) for each month. 2. Evaluate the company's performance over the last four months. 3-a. Refer to the data for month 4. Assume in month 5 the company uses Lean Production to completely eliminate the queue time, and all else remains the same as month 4. Compute the new throughput time and MCE. 3-b. Refer to the data for month 4. Assume in month 6 the company eliminates all queue time and inspection time, and all else remains the same as month 4 . Compute the new throughput time and MCE. Complete this question by entering your answers in the tabs below. 1-a. Compute the throughput time for each month. 1-b. Compute the delivery cycle time for each month. 1 -c. Compute the manufacturing cycle efficiency (MCE) for each month. Note: Round your answers to 1 decimal place. Required: 1.a. Compute the throughput time for each month. 1-b. Compute the delivery cycle time for each month. 1-c. Compute the manufacturing cycle efficiency (MCE) for each month. 2. Evaluate the company's performance over the last four months. 3-a. Refer to the data for month 4. Assume in month 5 the company uses Lean Production to completely eliminate the queue time, and all else remains the same as month 4. Compute the new throughput time and MCE. 3-b. Refer to the data for month 4. Assume in month 6 the company eliminates all queue time and inspection time, and all else remains the same as month 4 . Compute the new throughput time and MCE. Complete this question by entering your answers in the tabs below. Evaluate the company's performance over the last four months. Note: Indicate the effect of each trend by selecting "Favorable" or "Unfavorable" or "None" for no effect (1.e, zero variance). Required: 1-a, Compute the throughput time for each month. 1-b. Compute the dellvery cycle time for each month. 1-c. Compute the manufacturing cycle efficiency (MCE) for each month. 2. Evaluate the company's performance over the last four months. 3-a. Refer to the data for month 4. Assume in month 5 the company uses Lean Production to completely eliminate the queue time, and all else remains the same as month 4. Compute the new throughput time and MCE. 3-b. Refer to the data for month 4. Assume in month 6 the company elliminates all queue time and inspection time, and all else remains the same as month 4. Compute the new throughput time and MCE. Complete this question by entering your answers in the tabs below. 3-a. (Month 5) Refer to the data for month 4. Assume in month 5 the company uses Lean Production to completely eliminate the queue time, and all else remains the same as month 4 . Compute the new throughput time and MCE. 3-b. (Month 6) Refer to the data for month 4. Assume in month 6 the company eliminates all queue time and inspection time, and all else remains the same as month 4. Compute the new throughput time and MCE. Note: Round your answers to 1 decimal place