Question

1 Approved Answer

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity

Time (weeks)

Immediate Predecessor(s)

Activity

Time (weeks)

Immediate Predecessor(s)

A

7

E

3

B

B

7

F

5

B

C

2

A

G

10

C, E

D

1

A

H

6

D , F

Dave's earliest start (ES) and earliest finish (EF) are:

Activity

ES

EF

A

7

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions