Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES , EF , LS
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES EF LS LF and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
tableActivityTime weeksImmediate PredecessorsActivity,Time weeksAImmediate PredecessorsBFBCAGBDAHC E
Dave's earliest start ES and earliest finish EF are:
tableActivityESEFABCDEFGH
Dave's latest start LS and latest finish LF are:
tableActivityLSLFHGFEDCBA
The slack times are:
tableActivitySlackABCDEFGH
The total project completion time for Dave weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started