Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES , EF , LS
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determineES EFLS LF and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activitytimes:
Activity
Time weeks
Immediate Predecessors
A
B
C
A
D
A
Activity
Time weeks
Immediate Predecessors
E
B
F
B
G
C E
H
D F
Daves earliest startES and earliest finishEF are:
Daves latest startLS and latest finishLF are:
The slack timesare:
The activities on the critical path are
The total project completion time for Dave weeks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started