Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES , EF , LS

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determineES, EF,LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activitytimes:
Activity
Time (weeks)
Immediate Predecessor(s)
A
6
-
B
8
-
C
4
A
D
2
A
Activity
Time (weeks)
Immediate Predecessor(s)
E
4
B
F
5
B
G
10
C, E
H
8
D , F
Dave's earliest start(ES) and earliest finish(EF) are:
Dave's latest start(LS) and latest finish(LF) are:
The slack timesare:_______________________________
The activities on the critical path are___________________________
The total project completion time for Dave=_______ weeks
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Book Of Templates

Authors: Navaid Ur Rehman

1st Edition

9798719847344

More Books

Students also viewed these General Management questions

Question

What factors must you consider when making an oral presentation?

Answered: 1 week ago

Question

OUTCOME 4 Explain how labour relations differ around the world.

Answered: 1 week ago