Question
Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost
Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow.
2017 2018
Costs incurred during the year $450,000 $1,100,000
Total costs 1,050,000 50,000
Percentage of completion 30% 96.875%
Billings during the year 500,000 1,400,000
Cash collections during the year 400,000 1,400,000
Assume the Beavis recognizes revenue on the contract over time according to percentage of completion
Required
1. Compute the amounts of revenue and gross profit (or loss) to be recognized in 2017 and 2018. Please label whether it is a profit or loss.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started