Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost

Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow.

2017 2018

Costs incurred during the year $450,000 $1,100,000

Total costs 1,050,000 50,000

Percentage of completion 30% 96.875%

Billings during the year 500,000 1,400,000

Cash collections during the year 400,000 1,400,000

Assume the Beavis recognizes revenue on the contract over time according to percentage of completion

Required

1. Compute the amounts of revenue and gross profit (or loss) to be recognized in 2017 and 2018. Please label whether it is a profit or loss.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions