Day 1 2 4 5 6 7 8 9 10 P(x) 0.005 0.01 0.04 0.08 0.11 0.18 0.25 0.15 0.12 ? CDF ? ? ?
Day 1 2 4 5 6 7 8 9 10 P(x) 0.005 0.01 0.04 0.08 0.11 0.18 0.25 0.15 0.12 ? CDF ? ? ? ? ? ? ? ? ? 1. What is the probability that the project will be finished after day 5(i.e., from day 6 to day 10)