Deadline: 0 5 . 0 3 . 2 0 2 4 EcoTech Inc. is a sustainable technology company based in Istanbul, Turkey, specializing in the
Deadline:
EcoTech Inc. is a sustainable technology company based in Istanbul, Turkey, specializing in the
production of three types of renewable energy systems: Solar Panels, Biofuel Generators, and
Hydroelectric Generators. The company's factory is equipped to manufacture these products
according to demand forecasts provided by the Sales Department for the next four months, as
detailed in Table of the case study.
At the beginning of October, EcoTech Inc. employs workers at its factory, each capable of
working hours per month during regular hours at a rate of $ per hour. Additionally,
workers can work up to hours of overtime per month at a rate of $ per hour. The company
has the option to hire additional workers as needed, but incurs legal costs of $ per new hire,
with a monthly recruitment budget of $ set by the Human Resources Department.
In addition to inhouse production, EcoTech Inc. has the option to outsource a portion of the
monthly production of Biofuel Generators to a subcontractor. Any excess production beyond
monthly demand can be stored in inventory for future use, with unit inventory holding costs
calculated based on a monthly interest rate of The warehouse capacity at the factory is
limited to units for the total inventory of the three products. At the beginning of October, no
panel or generators are held in the inventory.
If a month's delivery cannot be fulfilled, backordering is permitted, allowing for late delivery of
demand with additional costs. However, all demand must be satisfied by the end of January.
For Solar Panels, Biofuel Generators, and Hydroelectric Generators, unit manufacturing costs,
unit subcontracting costs, backordering costs, and labor requirements are provided.
EcoTech Inc. aims to determine a monthly production plan for the three renewable energy
systems and a workforce plan for the fourmonth period, with the objective of minimizing total
costs. As consultants hired by the company,
a Formulate the problem as a linear programming LP model. Keep in mind that the model may
involve noninteger numbers of workers and vehicles.
b Utilize Excel Solver to solve the LP model, as the company lacks access to other optimization
packages.
c Conduct a comprehensive sensitivity analysis and compile the results into actionable
suggestions for presentation to the management of EcoTech Inc. Suggestions may include
considerations such as implementing a salary increase in January or negotiating terms with
subcontractors to optimize costs and improve efficiency.
pls write the LP model in both extended and algebraic form, show clearly the steps of how to solve this problem in excel solver
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started