Dear professor, Please help to solve this problem about the revenue recognition. Best regards, On December 31, Year 1 , SIS Steel Construction, signs a

Dear professor,

Please help to solve this problem about the revenue recognition.

Best regards,

image text in transcribed
On December 31, Year 1 , SIS Steel Construction, signs a contract with HBC to constructa new building. SIS Steel anticipates the construction will take 3 years from the end of year 1. The com pa ny's accountants provide the following contract details relating to the project: Contract price $624 million Estimated construction costs $480 million Estimated total profit $144 million During the first two years of construction, SIS Construction incurred costs as folllows: Jan-Dec Year 2 $48 million Jan-Dec Year 3 $288 million SIS Steel Construction uses the cost to cost method to recognize revenue. Compute revenue to be recognized and the estimated profit for : Year 2: Revenue 5 million ; and Estimated Profits million Year 3: Revenue 5 million ; and Estimated Profits million

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Theory And Analysis Text And Cases

Authors: Richard G Schroeder, Myrtle W Clark, Jack M Cathey

13th Edition

1119577772, 9781119577775

More Books

Students also viewed these Accounting questions

Question

3. Im trying to point out what we need to do to make this happen

Answered: 1 week ago

Question

1. I try to create an image of the message

Answered: 1 week ago