Dec 31 20xx Manufacturing Cost Budget Direct Materials Material Costs Unit Costs Total unit cost Plastic 306000 3.40/lb*1.5= 5.1 Motor 390000 6.50/set 6.5 Wheels/Axels 24000
Dec 31 20xx
Manufacturing Cost Budget
Direct Materials
Material Costs
Unit Costs
Total unit cost
Plastic\
306000 3.40/lb*1.5= 5.1
Motor
390000
6.50/set
6.5
Wheels/Axels
24000
.40/set
0.4
Total Direct Materials
$720,000.00
12
Direct Labor
Labor Costs
Unit Costs
Cost per Car
Molders
180000
15*0.2
3
Assemblers
324000
18*.3
5.4
Total Direct Labor
$504,000.00
8.4
Manuacturing Overhead
Cost
Cost Per Car
Variable OH
30000*5.50=165000
5.5
Fixed OH
30000*4.82=144600
4.82
Total FOH
$309,600.00
10.32
Total Manufacturing Costs:
$1,533,600.00
$30.72
During January 20XX, Speedway Toys, Inc., manufactured 4,800 toy cars. The costs of materials, labor, and overhead were as follows:
Material Amount
Plastic 7,050 lb at $3.60 per
lb
Motors 4,975 motors at $6.24
per motor
Wheels and axles 4,880 sets
at $.425 per set
Direct Labor
Hours Rate
Molders 930 hr $15.20 per
hour
Assemblers 1510 hr $18.40 per
hour
Overhead Amount
Variable $13,120
Fixed $12,050
You are to prepare the
following for the month of January 20XX. For all variances computed, show
whether they are favorable or unfavorable.
B-1 Complete summary of
materials costs.
B-2 Complete summary of
labor costs.
B-3 Compute the quantity and
price variances for each material.
B-4 Compute the efficiency
and rate variance for each type of labor.
B-5 Compute the total
manufacturing overhead variance. Analyze the total overhead variance, using the
three-variance analysis method.
B-6 Record the following in
general journal form (omit explanations):
a.Charge
the raw materials to production and record the materials
variances.
b.Charge
the labor to production and record the labor variances.
c.Charge
the manufacturing overhead to production and record the overhead variances.
d.Transfer
the completed units to finished goods.
I am having hard time
computing the standard cost for materials and labor. Can someone please help me
figure some of this problem out? If you need more information please let me
know. Thank you!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started