Declan is a project manager. He is currently leading the team through the Estimate Costs process. They are estimating a component of work. To do
Declan is a project manager. He is currently leading the team through the Estimate Costs process. They are estimating a component of work. To do this, they are estimating the cost of individual work packages to the greatest level of specified detail. Theyare then summarizing the detailed costs and providing it to higher levels for subsequent reporting and tracking purposes. What type of estimating is Declan utilizing