Declerque company makes flavored water and performs the following tasks in the beverage manufacturing process: Hours Receiving and transferring ingredients to storage 6 Storing ingredients
Declerque company makes flavored water and performs the following tasks in the beverage manufacturing process: Hours Receiving and transferring ingredients to storage 6 Storing ingredients 180 Transferring the ingredients from storage 3 Mixing and cooking the ingredients 3 Bottling the water 2 Transferring the bottles to await customer shipment6
a) Calculate the total cycle time of this manufacturing process.
b) Calculate the manufcaturing cycle efficiency of this process
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started