Question
Deep Mines Ltd. of Saskatchewan is contemplating the purchase of equipment to exploit a mineral deposit located on land to which the company has mineral
Deep Mines Ltd. of Saskatchewan is contemplating the purchase of equipment to exploit a mineral deposit located on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with opening and operating a mine in the area.
Cost of new equipment and timbers
$272,000
Working capital required Net annual cash receipts
93,000 126,000
Cost to construct new roads in three years
48,000
Salvage value of equipment in four years
50,000
*Receipts from sales of ore, less out of pocket costs for salaries, utilities, Insurance and so forth
It is estimated that the mineral deposit would be exhausted after four years of mining. At that point, the working capital would be released for reinvestment elsewhere. The company's discount rate is 20%.
Click here to view Exhibit 10-1 an
d Exhibit 10-2. to determine the appropriate discount factor(s) using tables
Required:
1-a. Determine the NPV of the proposed mining project (Negative amount should be indicated with a minus sign. Round discount factor(s) to 3 decimal places. Round other intermediate calculations and final answer to the nearest whole number.)
Net present value
1-b. Should the project be accepted?
Deep Mines Ltd. of Saskatchewan is contemplating the purchase of equipment to exploit a mineral d the company has mineral rights. An engineering and cost analysis has been made, and it is expectec would be associated with opening and operating a mine in the area: "Receipts from sales of ore, less out-of-pocket costs for salaries, utilities, insurance and so forth. It is estimated that the mineral deposit would be exhausted after four years of mining. At that point, released for reinvestment elsewhere. The company's discount rate is 20%. Click here to view Exhibit 10-1 and Exhibit 10-2, to determine the appropriate discount factor(s) using Required: 1-a. Determine the NPV of the proposed mining project (Negative amount should be indicated with factor(s) to 3 decimal places. Round other intermediate calculations and final answer to the neareStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started