DEF Project Management has started a project, that is expected to be completed over 3-days, 8-hours per day. What are total project costs based on
DEF Project Management has started a project, that is expected to be completed over 3-days, 8-hours per day. What are total project costs based on the information listed in the table below? Electrical & Lighting $500 Supplies $1,000 Furniture $2,000 Location Permits $400 Producer $65.00 per hour Director $75.00 per hour Actor 1 $45.00 per hour Actor 2 $45.00 per hour Question 14 options: $9,500 $9,420 $5,520 $3,900 $5,750