Demand history for the past three years is shown below. The network diagram and task times for a project are shown below. *3? Task Duration
Demand history for the past three years is shown below.
The network diagram and task times for a project are shown below. *3? Task Duration (days) A1 4 A2 7 A3 4 A4 3 A5 1 What is the slack for activity A3? : EdaysStep by Step Solution