Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Denny Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The companys estimator has been involved in a long-simmering dispute with

Denny Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The companys estimator has been involved in a long-simmering dispute with the on-site work supervisors. The on-site supervisors claim that the estimator does not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $6,000 per thousand square feet to determine the bid price. Since our average cost is only $3,000 per thousand square feet, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or nonroutine until you actually start tearing things apart.

To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square feet 520 thousand square feet
Estimating and job setup Number of jobs 160 jobs*
Working on nonroutine jobs Number of nonroutine jobs 28 nonroutine jobs
Other (organization-sustaining and idle capacity costs) None Not applicable

* The total number of jobs includes nonroutine jobs as well as routine jobs. Nonroutine jobs as well as routine jobs require estimating and setup work.

Costs for the Year
Wages and salaries $ 207,000
Disposal fees 608,000
Equipment depreciation 16,000
On-site supplies 59,000
Office expenses 187,000
Licensing and insurance 372,000
Total cost $ 1,449,000

Distribution of Resource Consumption Across Activities

Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries 33 % 12 % 31 % 24 % 100 %
Disposal fees 73 % 0 % 27 % 0 % 100 %
Equipment depreciation 43 % 0 % 37 % 20 % 100 %
On-site supplies 52 % 11 % 18 % 19 % 100 %
Office expenses 7 % 36 % 27 % 30 % 100 %
Licensing and insurance 41 % 0 % 32 % 27 % 100 %

Required:
1.

Perform the first-stage allocation of costs to the activity cost pools.

2. Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places.)

3.

Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system. (Round your intermediate and final answers to 2 decimal places.)

a. A routine 4,000-square-foot asbestos removal job.

b. A routine 6,000-square-foot asbestos removal job.

c. A nonroutine 4,000-square-foot asbestos removal job.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting For Beginners

Authors: Nicholas Apostolides

1st Edition

0815351224, 978-0815351221

More Books

Students also viewed these Accounting questions

Question

main.pl

Answered: 1 week ago

Question

2 What are the psychological stages of coping with change?

Answered: 1 week ago

Question

6 Why is change considered a central aspect of HRM practice?

Answered: 1 week ago