Denny Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The companys estimator has been involved in a long-simmering dispute with

Denny Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The companys estimator has been involved in a long-simmering dispute with the on-site work supervisors. The on-site supervisors claim that the estimator does not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $4,000 per thousand square feet to determine the bid price. Since our average cost is only $3,000 per thousand square feet, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or nonroutine until you actually start tearing things apart.

To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square feet 500 thousand square feet
Estimating and job setup Number of jobs 170 jobs*
Working on nonroutine jobs Number of nonroutine jobs 26 nonroutine jobs
Other (organization-sustaining and idle capacity costs) None Not applicable

* The total number of jobs includes nonroutine jobs as well as routine jobs. Nonroutine jobs as well as routine jobs require estimating and setup work.

Costs for the Year
Wages and salaries $ 208,000
Disposal fees 599,000
Equipment depreciation 64,000
On-site supplies 59,000
Office expenses 194,000
Licensing and insurance 365,000
Total cost $ 1,489,000

Distribution of Resource Consumption Across Activities

Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries 31 % 10 % 25 % 34 % 100 %
Disposal fees 69 % 0 % 31 % 0 % 100 %
Equipment depreciation 42 % 0 % 30 % 28 % 100 %
On-site supplies 51 % 13 % 16 % 20 % 100 %
Office expenses 5 % 36 % 30 % 29 % 100 %
Licensing and insurance 43 % 0 % 36 % 21 % 100 %

Required:
1.

Perform the first-stage allocation of costs to the activity cost pools. (Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)

Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries $ $ $ $ $
Disposal fees
Equipment depreciation
On-site supplies
Office expenses
Licensing and insurance
Total cost $ $ $ $ $

2. Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places. Omit the "$" sign in your response.)

Activity Cost Pool Activity Rate
Removing asbestos $ per thousand square feet
Estimating and job setup $ per job
Working on nonroutine jobs $ per nonroutine job

3.

Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system. (Round your intermediate and final answers to 2 decimal places. Omit the "$" sign in your response.)

a. A routine 2,000-square-foot asbestos removal job.

Total cost of the job $
Average cost per thousand square feet $

b. A routine 4,000-square-foot asbestos removal job.

Total cost of the job $
Average cost per thousand square feet $

c. A nonroutine 2,000-square-foot asbestos removal job.

Total cost of the job $
Average cost per thousand square feet $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Activity Based Cost Management In Government

Authors: Gary Cokins

2nd Edition

1567261817, 978-1567261813

More Books

Students also viewed these Accounting questions

Question

Does your strategic intent lay out the priorities?

Answered: 1 week ago