Determine over- and underbillings and job percent complete for a company with the following information: Job Number: 221 Job Name: Frank Office Remodel Current Contract
Determine over- and underbillings and job percent complete for a company with the following information:
Job Number: 221 Job Name: Frank Office Remodel Current Contract Amount: $22,530 Total Estimated Cost at Completion: $17,264 Actual Costs to Date: $16,538 Total Billed: $21,000
Job Number: 222 Job Name: Hawkes Market Remodel Current Contract Amount: $35,624 Total Estimated Cost at Completion: $28,221 Actual Costs to Date: $22,345 Total Billed: $28,500
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started