Determine over- and underbillings for a company with the following information Job Number: 20-318 Job Name: Mountain Peak Office Remodel Current Contract Amount: $256,852 Total
- Determine over- and underbillings for a company with the following information
Job Number: 20-318
Job Name: Mountain Peak Office Remodel
Current Contract Amount: $256,852
Total Estimated Cost at Completion: $225,236
Actual Costs to Date: $202,138
Total Billed: $252,253
Job Number: 20-319
Job Name: Market Street Warehouse
Current Contract Amount: $55,123
Total Estimated Cost at Completion: $45,224
Actual Costs to Date: $5,211
Total Billed: $5,500
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started