Question
Determining the Transaction Price for a Revenue Contract A contractor enters into a revenue contract with a customer to build customized equipment for $100,000 with
Determining the Transaction Price for a Revenue Contract
A contractor enters into a revenue contract with a customer to build customized equipment for $100,000 with a performance bonus of $55,000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar contracts and thus has the data to predict the timing of completion of the contract. Therefore, the contractor concludes that the expected value method is the best predictor of revenue. The contractor estimates that there is a 65% probability that the contract will be completed by the agreed-upon completion date, a 25% probability that it will be completed one week late, and a 10% probability that it will be completed two weeks late.
Complete the following table in order to determine the transaction price for revenue recognition for the contractor. Round each amount in the table to the nearest dollar.
Consideration | Bonus Amount | Probability of Outcome | Revenue Recognized |
---|---|---|---|
Bonus if completed on agreed-upon date | Answer | Answer | Answer |
Bonus if completed one week late | Answer | Answer | Answer |
Bonus if completed two weeks late | Answer | Answer | Answer |
Variable consideration | Answer | ||
Fixed consideration | Answer | ||
Total transaction price | Answer |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started