Question

1 Approved Answer

Develop a EOQ solution and calculate total relevant costs for the gross requirements in the following table*. Period Gross requirements 5 6 7 8 9

Develop a EOQ solution and calculate total relevant costs for the gross requirements in the following table*. Period Gross requirements 5 6 7 8 9 30 20 30 *Holding cost = $2.50/unit/week; setup cost = $150; lead time = 1 week; beginning inventory = 40. $ The total cost is $ Period Gross requirements Scheduled receipt Projected On-hand Setup cost for 12 weeks is $ Carrying cost for 12 weeks is Net Requirements Planned Order receipt Planned Order release What is the average demand per week? (enter your responses with 2 decimal places): Calculate Economic Order Quantity (EOQ) (enter your responses as whole numbers): Calculate the number of periods for POQ (enter your responses as whole numbers): Develop a POQ solution (enter your responses as whole numbers). 1 30 (enter your response as a whole number). 2 40 1 30 3 40 (enter your response as a whole number). 4 2 (enter your response as a whole number). 3 40 10 10 20 11 4 5 6 7 8 9 30 20 30 10 12 50 10 11 12 20 50
image text in transcribed
image text in transcribed
"Holding cost =$2.50/ unit/week; setup cost =$150; lead time =1 week; beginning inventory =40. What is the average demand per week? (enter your responses with 2 decimal places): Calculate Economic Order Quantity (EOQ) (enter your responses as whole numbers): Caiculate the number of periods for POQ (onter your responses as whole numbers): Develop a POQ solution (enter your responses as wholo numbers). Setup cost for 12 weeks is $ (enter your response as a whole number). Carrying cost for 12 weeks is $ (enter your response as a whole number). The total cost is $ (enter your response as a whole number). "Holding cost =$2.50/ unit/week; setup cost =$150; lead time =1 week; beginning inventory =40. What is the average demand per week? (enter your responses with 2 decimal places): Calculate Economic Order Quantity (EOQ) (enter your responses as whole numbers): Calculate the number of periods for POQ (enter your responses as whole numbers): Develop a POQ solution (enter your responses as whole numbers). Setup cost for 12 weeks is $ (enter your response as a whole number). Carrying cost for 12 weeks is $ (entor your responso as a wholo number). The total cost is $ (enter your rosponse as a whole number)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Great Boss Great Management

Authors: S. M. H. Gibson

1st Edition

9798842893430

More Books

Students also viewed these General Management questions