Develop a line of balance schedule for a 20-housing unit project considering that each unit has the
Fantastic news! We've Found the answer you've been seeking!
Question:
Develop a line of balance schedule for a 20-housing unit project considering that each unit has the activities shown in the Table below, the hand-over rate is 3units per week and the contractor is planning to work 40 hours per week and use 5 days buffer between activities
Activity | Man-Hours per Activity | Man per actvity |
A Substructure | 110 | 3 |
B Superstructure | 320 | 8 |
C Joinery | 365 | 9 |
D Pluming | 35 | 2 |
E finishes | 210 | 5 |