Question

1 Approved Answer

Develop a line of balance schedule for a 20-housing unit project considering that each unit has the activities shown in the Table below, the hand-over

Develop a line of balance schedule for a 20-housing unit project considering that each unit has the activities shown in the Table below, the hand-over rate is 3units per week and the contractor is planning to work 40 hours per week and use 5 days buffer between activities

Activity Man-Hours per Activity Man per actvity
A Substructure 110 3
B Superstructure 320 8
C Joinery 365 9
D Pluming 35 2
E finishes 210 5

Step by Step Solution

3.32 Rating (140 Votes )

There are 3 Steps involved in it

Step: 1

Answer and detailed step by step explanation Line of Balance Schedule Week 1 A Substructure 3 people x 110 manhours 330 manhours Week 2 B Superstructu... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions

Question

What is the security goal of non repudiation

Answered: 1 week ago

Question

Discuss the scope of Human Resource Management

Answered: 1 week ago

Question

Discuss the different types of leadership

Answered: 1 week ago

Question

Write a note on Organisation manuals

Answered: 1 week ago

Question

Define Scientific Management

Answered: 1 week ago

Question

Explain budgetary Control

Answered: 1 week ago