Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Draw the precedence diagram for the set of tasks.
Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
- Draw the precedence diagram for the set of tasks.
- Calculate the theoretical minimum number of workstations.
- Balance this line by assigning tasks to stations.
- Does the solution have the minimum number of stations? Explain.
- How much idle time is there, summed over all workstations?
- What is the efficiency of this line?
Work Task | Task Time (seconds) | Task Predecessor(s) |
A | 70 | - |
B | 60 | A |
C | 120 | B |
D | 60 | - |
E | 240 | C,D |
F | 100 | A |
G | 190 | E,F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started