Develop and build the following project schedule. MS Project (or any scheduling software) is not to be used Use sticky notes, PowerPoint, Excel, Word, Visio,

Develop and build the following project schedule.

  • MS Project (or any scheduling software) is not to be used
  • Use sticky notes, PowerPoint, Excel, Word, Visio, or any drawing-type software

Directions

  1. Use the table below to develop a precedence diagram
  2. Identify the early start and early finish for each task
  3. Identify the late start and late finish for each task
  4. Identify the float in each task
  5. Identify any tasks that have free float
ActivityImmediate Preceding ActivityDuration
a. Excavate-5
b. Foundationa2
c. Frameb12
d. Electricc9
e. Roofc5
f. Brickc8
g. Finish interiord10
h. Finish exteriord7
i. Landscape
 
h5

Step by Step Solution

3.33 Rating (147 Votes )

There are 3 Steps involved in it

Step: 1

While I cannot create a visual diagram directly I can provide detailed instructions and a textual re... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

Define the term annuity. What is one example of an annuity receipt?

Answered: 1 week ago